The City of Winter Park is reviewing interlocal agreements for sewage treatment capacity. These agreements are with the City of Orlando and the City of Altamonte Springs. The City of Winter Park has committed capacity totaling 7,675,524 gallons per day from these sources. The City does not own or operate these facilities, nor does it have an equity interest in them. The City funds its share of operating costs based on its committed and used capacity. This item is currently under review by the City Commission. While no direct construction is outlined, these agreements support ongoing utility operations and potential future infrastructure needs related to sewage treatment.
- Orlando McLeod capacity
- 1000000 gallons per day
- Orlando Iron Bridge I capacity
- 4962000 gallons per day
- Orlando Iron Bridge II capacity
- 1000000 gallons per day
- Altamonte Springs capacity
- 713524 gallons per day
- Total Committed Capacity
- 7675524 gallons per day
Industries that could win this work
- Utilities (Sub)
Follow this across meetings
Board
City CommissionApplicants and firms
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account