2) Environmental - Additional Blowers for MIP WWTP

Commission Committee Meeting · 2026-05-19 · agenda_item

Santa Rosa County is considering a change order for the MIP Wastewater Treatment Plant (WWTP). This change order, if approved, would add blowers to expand the plant's capacity from 0.25 million gallons per day (MGD) to 0.5 MGD. The proposed cost for this expansion is $50,830. This item is currently under review by the Commission Committee. If approved, the project would involve the installation of new equipment and potentially related utility connections. Contractors and suppliers involved in wastewater treatment equipment, installation, and related services could find opportunities. Early engagement before final permits and bidding may offer an advantage.

change order amount
50830 $
original capacity
0.25 MGD
expanded capacity
0.5 MGD

Industries that could win this work

  • Utilities (Sub)
  • General Contractor
  • HVAC & Climate Control
  • Plumbing
  • Building & Industrial Supply

Follow this across meetings

Applicants and firms

Locations

See the actual businesses behind these numbers

Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.

Create your account