2. All terms and conditions of the previous Agreement and Amendments, which are
City Council · 2026-05-05 · agenda_item
The City of West Melbourne is considering a project to patch four sections of Doherty Drive. This work involves milling down two inches and installing two inches of new asphalt. The proposed work is planned and has been recommended for approval. The project will involve site preparation, including milling existing asphalt, followed by paving operations. Contractors specializing in asphalt paving and related site work may find opportunities. Reaching out to the city early in the process could provide an advantage before final bids and permits are settled.
- weighted points
- 24
- milling depth
- 2 inches
- asphalt installation depth
- 2 inches
- section 1 length
- 50 feet
- section 1 width
- 16 feet
- section 2 length
- 50 feet
- section 2 width
- 16 feet
- section 3 length
- 200 feet
- section 3 width
- 14 feet
- section 4 length
- 25 feet
- section 4 width
- 22 feet
Industries that could win this work
- Site Prep, Grading & Hardscape
- Concrete & Masonry
- General Contractor
- Building & Industrial Supply
Follow this across meetings
Board
City CouncilApplicants and firms
Locations
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account