17. RULES AND REGULATIONS. Landlord has certain rules and regulations applicable to
City Commission Meeting · 2026-04-13 · agenda_item
The City of Leesburg is reviewing an agreement to provide electric service to a new development called The Enclave at Lake Geneva. This development is planned by Fruitland Park Development IV, LLC. The project involves extending electric lines and performing make-ready work to serve 279 new homes. The agreement also includes installing 46 streetlights and related fixtures, which will require additional conduit. This item is currently under review by the City Commission. The work will involve site preparation for utility extensions, installation of underground electrical systems, and potentially street lighting installation. Contractors and suppliers involved in electrical utility work, site preparation, and lighting installation may find opportunities. Early engagement before final bids and permits could be advantageous.
- metered units
- 279
- developer's costs for line extension
- 218217.18
- developer's costs for make-ready work
- 9885.08
- payment from Fruitland Park Development, LLC
- 228216.27
- bond amount
- 789291.00
- streetlights
- 46
- cost for additional conduit
- 1114.01
- monthly invoice for capital costs, energy, and O&M
- 978.00
Industries that could win this work
- Electrical
- Site Prep, Grading & Hardscape
- Utilities (Sub)
- Building & Industrial Supply
- Engineering & Architecture
Follow this across meetings
Applicants and firms
Locations
See the actual businesses behind these numbers
Get the real filings, with addresses and officers, backed by a 14-day money-back guarantee.
Create your account