Board of County Commissioners: July 2026
Miami-Dade County
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's average daily flow capacity and peak flow capacity. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. Small Business Enterprise measures were applied to the original contract but do not apply to this time extension change order.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Resolution ratifying action by the County Mayor or County Mayor’s designee; approval of Change Order No. 1
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, with the Notice to Proceed issued on May 2, 2022. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution adopted on 7/21/2026 ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. Change Order No. 1 grants a 622-calendar day non-compensable time extension, extending Substantial Completion Date from June 10, 2023 to February 21, 2025, and Final Completion Date from July 22, 2023 to April 4, 2025. No additional fiscal impact. Project increases permitted average annual daily flow from 112.5 to 131 MGD and peak flow capacity from 285 to 305 MGD. Contract awarded March 1, 2022, ratified May 17, 2022 via Resolution No. R-491-22, total award $21,805,340.00. Notice to Proceed issued May 2, 2022. Delays: 415 days for electrical equipment fabrication/delivery, 207 days for low voltage wire pulls requiring shutdown of Headworks Building No. 1 until dry season December 1, 2024. SBE goals: 11.85% SBE-Construction, 1% SBE-Goods. Resolution No. R-525-17 exempts non-compensatory time extensions from Resolution No. R-1001-15 compliance.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution adopted on 7/21/2026 ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. Change Order No. 1 grants a 622-day non-compensable time extension, extending Substantial Completion from June 10, 2023 to February 21, 2025, and Final Completion from July 22, 2023 to April 4, 2025. No additional fiscal impact. Project increases permitted average annual daily flow from 112.5 to 131 MGD and peak flow from 285 to 305 MGD. Contract awarded March 1, 2022, ratified May 17, 2022 via Resolution R-491-22, total award $21,805,340.00. Project located in Commission District 8. No public comment sentiment stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project aims to increase the plant's average annual daily flow capacity and peak flow capacity. The time extension is due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and operational shutdown sequencing constraints for installing new voltage feeders. The original contract award was $21,805,340.00. The Substantial Completion Date will be extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact to the County. The contract had SBE-Construction and SBE-Goods goals, but these do not apply to this time extension change order.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is set to ratify Change Order No. 1 to Contract No. S-930B with Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project aims to increase the plant's average daily flow capacity from 112.5 to 131 million gallons per day and peak flow capacity from 285 to 305 MGD. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The contract had SBE-Construction and SBE-Goods goals, but Resolution R-525-17 exempts this time extension from compliance review.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Resolution ratifying action by the County Mayor or County Mayor’s designee approving Change Order No. 1
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. This change order grants a 622-day non-compensable time extension due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's average daily flow capacity and peak flow capacity. The change order extends the Substantial Completion Date from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. The original contract award was $21,805,340.00.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (Resolution ratifying action)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension with no additional fiscal impact. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks, and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The contract was awarded on March 1, 2022, ratified by the Board on May 17, 2022 via Resolution No. R-491-22, for a total contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. The project is located in Commission District 8, represented by Commissioner Danielle Cohen Higgins. The delays were due to electrical equipment fabrication and delivery delays (415 days) and low voltage wire pulls delay (207 days) requiring shutdown of Headworks Building No. 1. The contract had an 11.85 percent Small Business Enterprise (SBE) - Construction goal and a one percent SBE - Goods goal. Resolution No. R-525-17 exempted non-compensatory time extensions from the 85 percent small business measure requirement. The Board adopted the resolution on July 21, 2026.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner)
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's treatment capacity. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. Small Business Enterprise measures from the original contract are not applicable to this time extension change order.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Resolution in Draft)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, with a total award of $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The project is located in Commission District 8. The resolution was adopted on July 21, 2026. No public comment sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner)
S-930B - DANIEL O'CONNELL'S SONS
The document is a resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project will increase the permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD at the SDWWTP. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The project is located in Commission District 8. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks, and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The contract was awarded on March 1, 2022, for $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The decision was adopted on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension due to fabrication and delivery delays of electrical equipment and required shutdowns for installation. The project aims to increase the SDWWTP's average daily flow capacity from 112.5 to 131 MGD and peak flow capacity from 285 to 305 MGD. The original contract award was $21,805,340.00. The Substantial Completion Date will be extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The change order has no additional fiscal impact. Small Business Enterprise (SBE) goals were applied to the original contract, but Resolution No. R-525-17 exempts this time extension from SBE compliance review.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (Pending BCC Assignment for ratification)
- Address:
- South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's capacity. The original contract award was $21,805,340.00. The Substantial Completion Date will be extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. Small Business Enterprise measures were applied to the original contract.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (for ratification of Change Order No. 1)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
The document is a resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project supports increasing the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The resolution was adopted by the Board of County Commissioners on July 21, 2026. The contract was awarded on March 1, 2022, with a total award of $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The document does not state a specific street address, parcel/folio, or acreage for the project, only that it is located in Commission District 8. The document does not state any public comment or stakeholder sentiment.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner)
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners ratified Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The original contract award was $21,805,340.00. The project aims to increase the SDWWTP's permitted average annual daily flow from 112.5 to 131 MGD and peak flow capacity from 285 to 305 MGD. The time extension is due to extended fabrication and delivery delays of electrical equipment (415 days) caused by supply chain issues and required shutdowns for installing new voltage feeders (207 days). The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The contract had SBE-Construction and SBE-Goods goals, but Resolution R-525-17 exempted this time extension from compliance review. No public comment was stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratified Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The project is located in Commission District 8. The resolution was adopted on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
The document is a resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's treatment capacity. The original contract award was $21,805,340.00. The Substantial Completion Date will be extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. Small Business Enterprise (SBE) goals were met on the original contract, and the exemption for non-compensatory time extensions applies.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Resolution in Draft)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project aims to increase the plant's average annual daily flow capacity and peak flow capacity. The time extension is due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and required shutdowns for installing new voltage feeders. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (Resolution ratifying action)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
This legislative item concerns Miami-Dade County's Water and Sewer Department's Consent Decree and Capital Improvement Programs Acceleration Ordinance. It seeks ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The extension is due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's average daily flow capacity and peak flow capacity. The change order extends the Substantial Completion Date from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The original contract award was $21,805,340.00.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Resolution in Draft)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
This legislative item concerns Miami-Dade County's Water and Sewer Department's Consent Decree and Capital Improvement Programs Acceleration Ordinance. It seeks ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. The change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and required shutdowns for installing new voltage feeders. The project aims to increase the SDWWTP's average daily flow capacity and peak flow capacity. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The contract had SBE-Construction and SBE-Goods goals.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Resolution ratifying action by the County Mayor or County Mayor’s designee, specifically approval of Change Order No. 1.
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The extension is due to extended fabrication and delivery delays of electrical equipment (415 days) and required shutdowns for new voltage feeder installation (207 days). The project aims to increase the SDWWTP's average daily flow capacity and peak flow capacity. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. The contract had SBE-Construction and SBE-Goods goals, but Resolution R-525-17 exempts this time extension from compliance review.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (pending BCC Assignment for ratification)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Daniel O'Connell's Sons, Inc. (contractor)
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, with the Notice to Proceed issued on May 2, 2022. The resolution was adopted on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
The document is a legislative item for Miami-Dade County, File Number 261212, a Resolution (Reference R-646-26) adopted by the Board of County Commissioners on 7/21/2026. It ratifies Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, with no additional fiscal impact. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project supports increasing the Plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The Contract was awarded on March 1, 2022, ratified by the Board on May 17, 2022 via Resolution No. R-491-22, for a total Contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. Change Order No. 1 extends the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The work is performed at WASD's SDWWTP, located in Commission District 8, represented by Commissioner Danielle Cohen Higgins. The document does not state a specific street address, parcel, or acreage. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner)
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension, with no additional fiscal impact. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. Substantial Completion Date extended from June 10, 2023 to February 21, 2025; Final Completion Date extended from July 22, 2023 to April 4, 2025. The contract was awarded on March 1, 2022, ratified by the Board on May 17, 2022 via Resolution No. R-491-22, for a total contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. The project is located in Commission District 8, represented by Commissioner Danielle Cohen Higgins. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution R-646-26 ratified Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-calendar day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project supports increasing the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, ratified by Resolution No. R-491-22 on May 17, 2022, for a total contract award of $21,805,340.00. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Daniel O'Connell's Sons, Inc. (Contractor)
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project aims to increase the plant's average daily flow capacity and peak flow capacity. The time extension is due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and required shutdowns for installing new voltage feeders. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact. The contract had SBE-Construction and SBE-Goods goals.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (Resolution ratifying action)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution adopted on 7/21/2026 ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. Change Order No. 1 grants a 622-calendar day non-compensable time extension. The project increases permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. Substantial Completion Date extended from June 10, 2023 to February 21, 2025; Final Completion Date extended from July 22, 2023 to April 4, 2025. Contract awarded on March 1, 2022, ratified by Board on May 17, 2022 via Resolution No. R-491-22, total contract award $21,805,340.00. Notice to Proceed issued May 2, 2022. No additional fiscal impact. No public comment or stakeholder sentiment stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project aims to increase the plant's average annual daily flow capacity and peak flow capacity. The time extension is due to delays in electrical equipment fabrication and delivery caused by supply chain issues, and required shutdowns for installing new voltage feeders. The original contract award was $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. There is no additional fiscal impact to the County. The project is located at the South District Wastewater Treatment Plant.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- In Draft (Resolution ratifying action)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project involves constructing two new electrical substations, installing new electrical equipment duct banks, and associated infrastructure to redistribute electrical loads. The delays are attributed to extended fabrication and delivery of electrical equipment due to supply chain issues and operational shutdown sequencing for installing new low voltage feeders. The project aims to increase the SDWWTP's average daily treatment capacity from 112.5 MGD to 131 MGD and peak flow capacity from 285 MGD to 305 MGD. The change order extends the Substantial Completion Date from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The original contract award was $21,805,340.00.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment (Resolution in Draft)
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
The Board of County Commissioners adopted Resolution R-646-26, ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-day non-compensable time extension, with no additional fiscal impact. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project will increase the Plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The contract was awarded on March 1, 2022, ratified by the Board on May 17, 2022 via Resolution No. R-491-22, for a total contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. The project is located at WASD's SDWWTP in Commission District 8. The delays were due to electrical equipment fabrication and delivery delays (415-calendar days) and low voltage wire pulls delay (207-calendar days) related to required shutdowns of Headworks Building No. 1. The contract was awarded with an 11.85 percent Small Business Enterprise (SBE) - Construction goal and a one percent SBE - Goods goal.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-calendar day non-compensable time extension with no additional fiscal impact. The project increases the permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD at the SDWWTP. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. Substantial Completion Date extended from June 10, 2023 to February 21, 2025; Final Completion Date extended from July 22, 2023 to April 4, 2025. Contract awarded March 1, 2022, ratified May 17, 2022 via Resolution No. R-491-22, total contract award $21,805,340.00. Notice to Proceed issued May 2, 2022. Adopted by Board of County Commissioners on July 21, 2026. File Number 261212, Resolution R-646-26. Location is Commission District 8, represented by Commissioner Danielle Cohen Higgins. No public comment sentiment stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner); Miami-Dade Water and Sewer Department (WASD) (Requester)
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-calendar day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project, originally awarded on March 1, 2022, for $21,805,340.00, involves construction of two new electrical substations and associated infrastructure to increase the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The change order was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. This change order grants a 622-day non-compensable time extension due to delays in electrical equipment fabrication and delivery, and required shutdowns for installation. The project aims to increase the SDWWTP's average daily flow capacity from 112.5 to 131 million gallons per day and peak flow capacity from 285 to 305 MGD. The original contract award was $21,805,340.00. The change order extends the Substantial Completion Date from June 10, 2023, to February 21, 2025, and the Final Completion Date from July 22, 2023, to April 4, 2025. The project involves constructing two new electrical substations, installing new electrical equipment duct banks, and associated infrastructure. The change order has no additional fiscal impact. The contract had SBE-Construction and SBE-Goods goals, but these are not applicable to this time extension change order.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Resolution ratifying action by the County Mayor or County Mayor’s designee related to approval of Change Order No. 1
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution adopted on 7/21/2026 ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. Change Order No. 1 grants a 622-calendar day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. No additional fiscal impact. The project increases the permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, ratified on May 17, 2022 via Resolution No. R-491-22, for a total contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. The project is located in Commission District 8. The contract has an 11.85 percent Small Business Enterprise (SBE) - Construction goal and a one percent SBE - Goods goal.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. Change Order No. 1 grants a 622-day non-compensable time extension. The project increases permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks, and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The work includes demolition and replacement of existing electrical components, integrations of new switchgear, transformers, RTUs and programmable logic controllers, and related site, civil, structural and electrical improvements. The project is located at WASD's SDWWTP in Commission District 8. The resolution was adopted on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-calendar day non-compensable time extension with no additional fiscal impact. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project will increase the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The Notice to Proceed was issued May 2, 2022. Change Order No. 1 extends the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The delays were due to extended fabrication and delivery delays of major electrical equipment (415-calendar day delay) and required shutdowns for installation and termination of new low voltage (480V) feeders serving existing facilities, including Headworks Building No. 1 (207-calendar day delay). The project is located at WASD's SDWWTP in Commission District 8, represented by Commissioner Danielle Cohen Higgins. The resolution was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc. (Contractor); Miami-Dade County (Owner)
S-930B - DANIEL O'CONNELL'S SONS
Miami-Dade County Board of County Commissioners is considering ratification of Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. This change order grants a 622-day non-compensable time extension for the construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The project involves constructing two new electrical substations, installing new electrical equipment, duct banks, and associated infrastructure to redistribute electrical loads, and includes demolition and replacement of existing electrical components. The delays are attributed to extended fabrication and delivery times for electrical equipment due to supply chain issues and operational shutdown sequencing constraints for installing new low voltage feeders. The project aims to increase the SDWWTP's permitted average annual daily flow from 112.5 to 131 MGD and peak flow capacity from 285 to 305 MGD, enhancing facility hardening for continuous operation during severe weather. The original contract award was $21,805,340.00. The change order has no additional fiscal impact. The Small Business Enterprise (SBE) goals for the original contract were 11.85% for Construction and 1% for Goods.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Pending BCC Assignment
- Address:
- South District Wastewater Treatment Plant (SDWWTP)
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for construction of ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16. The change order grants a 622-day non-compensable time extension with no additional fiscal impact. The project increases the permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD at the SDWWTP. The project consists of construction of two new electrical substations, installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. Substantial Completion Date extended from June 10, 2023 to February 21, 2025; Final Completion Date extended from July 22, 2023 to April 4, 2025. Contract awarded March 1, 2022, ratified May 17, 2022 via Resolution No. R-491-22 for $21,805,340.00. Notice to Proceed issued May 2, 2022. Delays: 415-calendar day extension for electrical equipment fabrication and delivery delay due to COVID-19 supply chain disruptions; 207-calendar day extension for low voltage wire pulls delay requiring shutdown of Headworks Building No. 1 until dry season commencement December 1, 2024. Small Business Enterprise goals: 11.85 percent SBE-Construction and 1 percent SBE-Goods. Resolution No. R-525-17 exempts non-compensatory time extensions from Resolution No. R-1001-15 requirements. Adopted by Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment stated in document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. The change order grants a 622-calendar day non-compensable time extension with no additional fiscal impact. The project involves construction of two new electrical substations and installation of new electrical equipment duct banks and associated infrastructure to redistribute electrical loads of oxygenation trains 1 through 8. The project will increase the permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD at the SDWWTP. The Substantial Completion Date is extended from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The contract was awarded on March 1, 2022, ratified by the Board on May 17, 2022 via Resolution No. R-491-22, for a total contract award of $21,805,340.00. The Notice to Proceed was issued on May 2, 2022. The project is located in Commission District 8, represented by Commissioner Danielle Cohen Higgins. The delays were due to electrical equipment fabrication and delivery delays (415-calendar days) and low voltage wire pulls delay (207-calendar days) requiring shutdown of Headworks Building No. 1. The decision was adopted by the Board of County Commissioners on July 21, 2026. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
S-930B - DANIEL O'CONNELL'S SONS
Resolution adopted on 7/21/2026 ratifying Change Order No. 1 to Contract No. S-930B between Miami-Dade County and Daniel O'Connell's Sons, Inc. for the ST-2D-B South District Wastewater Treatment Plant (SDWWTP) Substations 5/6 and 15/16 project. Change Order No. 1 grants a 622-calendar day non-compensable time extension, extending the Substantial Completion Date from June 10, 2023 to February 21, 2025, and the Final Completion Date from July 22, 2023 to April 4, 2025. The project increases the plant's permitted average annual daily flow from 112.5 to 131 million gallons per day (MGD) and peak flow capacity from 285 MGD to 305 MGD. The contract was awarded on March 1, 2022, for $21,805,340.00, ratified by Resolution No. R-491-22 on May 17, 2022. The project is located in Commission District 8. No public comment or stakeholder sentiment is stated in the document.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Resolution
- Decision:
- Adopted
- Applicant:
- Miami-Dade County Water & Sewer Department; Contractor: Daniel O'Connell's Sons, Inc.
SAME DAY PERMIT PROGRAM
Miami-Dade County is creating a Same-Day Permitting Program for certain residential projects. The program, to be implemented by the County Mayor or designee, will expedite permits for minor projects like fences (under 6 feet), gates, stairs, railings, driveways, pavers, trusses, pools, windows, doors, shutters, skylights, garage doors, roofing/re-roofing, kitchen/bathroom remodels, interior/partial demolition, prefabricated sheds, minor non-structural repairs, and mechanical, electrical, and plumbing repairs. Projects requiring structural review, those in historic districts, with open code enforcement cases, or to legalize violations are excluded. Applicants must submit documents electronically before a meeting for same-day review and potential approval. The County Mayor will report on the program's progress every six months. If delays are department-caused, permit fees may be reduced by 10% per business day. The ordinance was introduced on 7/14/2026 and is scheduled for Board of County Commissioners (BCC) action on 7/21/2026.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Pending BCC Assignment (introduced, forwarded to BCC with favorable recommendation with committee amendments)
- Applicant:
- Miami-Dade County Board of County Commissioners (requester: NONE, sponsor: Anthony Rodriguez)
SAME DAY PERMIT PROGRAM
Miami-Dade County is creating a Same-Day Permitting Program for certain minor residential projects. The program aims to streamline the permit application process for eligible projects such as fences (under six feet), gates, stairs, driveways, pools, windows, doors, roofing, kitchen/bathroom remodels, interior demolition, sheds, minor non-structural repairs, and MEP repairs. Projects requiring structural review, those in historic districts, with open code cases, or legalizing violations are excluded. Applicants will submit documents electronically for potential same-day review and approval. The County Mayor or designee will implement the program and provide six-month progress reports. Fee reductions may apply if delays are department-caused. The ordinance was introduced on July 14, 2026, and was before the Board on July 21, 2026.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Ordinance creating program, status is 'Before the Board' as of July 21, 2026.
- Applicant:
- County Mayor or County Mayor's designee (to develop and implement)
SAME DAY PERMIT PROGRAM
Ordinance creating Section 8-9 of the Code of Miami-Dade County, Florida, requiring the County Mayor or designee to develop and implement a same-day permitting program for certain permit applications for certain residential projects, with reports every six months. The ordinance lists eligible minor residential projects including fences (height equal to or less than six feet), gates, stairs and railings, driveways and pavers, trusses, pools, windows, doors, shutters, skylights, garage doors, roofing and re-roofing, kitchen or bathroom remodels, interior or partial demolition, prefabricated sheds, minor non-structural repairs, and mechanical, electrical, and plumbing repair permits. Projects requiring structural review, projects on properties within historic districts, projects on properties with open code enforcement cases, and projects to legalize existing violations are not eligible. The program is to be implemented through an implementing order approved by the Board of County Commissioners. Reports every six months must detail total applications submitted, approved same-day, not approved same-day, and reasons for delays. For applications not approved same-day, if delay factors were caused by the reviewing department rather than the applicant, the building permit fee shall be reduced by 10 percent per business day in accordance with section 553.792(1)(e), Florida Statutes. The ordinance becomes effective ten days after enactment unless vetoed by the Mayor. File Number: 261305. Introduced: 7/14/2026. Final Action: 7/21/2026. Status: Adopted. Prime Sponsor: Anthony Rodriguez. Co-Sponsors: Marleine Bastien, Sen. Rene Garcia, Vicki L. Lopez, Micky Steinberg. The Policy Council on 7/13/2026 forwarded to BCC with a favorable recommendation with committee amendments following public hearing. The Board of County Commissioners on 7/21/2026 adopted the ordinance. Commissioners Bastien and Steinberg asked to be listed as co-sponsors.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Adopted
SAME DAY PERMIT PROGRAM
Miami-Dade County is creating a Same-Day Permitting Program for certain minor residential projects. The program aims to expedite the permit process for eligible applications, including fences (under 6 feet), gates, stairs, railings, driveways, pavers, trusses, pools, windows, doors, shutters, skylights, garage doors, roofing/re-roofing, kitchen/bathroom remodels, interior/partial demolition, prefabricated sheds, minor non-structural repairs, and mechanical, electrical, and plumbing repairs. Projects requiring structural review, those in historic districts, with open code enforcement cases, or to legalize violations are ineligible. Applicants must submit documents electronically prior to a meeting for same-day review and potential approval. The County Mayor or designee will implement the program and provide six-month reports on its effectiveness. Permit fees may be reduced if delays are caused by the reviewing department. The ordinance was introduced on 7/14/2026 and scheduled for an agenda on 7/21/2026.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Pending BCC Assignment (introduced, forwarded to BCC with favorable recommendation with committee amendments)
- Applicant:
- County Mayor or County Mayor's designee (to develop and implement)
SAME DAY PERMIT PROGRAM
Miami-Dade County adopted Ordinance File Number 261305, creating Section 8-9 of the County Code to establish a Same-Day Permitting Program for certain minor residential projects. The ordinance requires the County Mayor or designee to develop and implement the program, covering specific project types such as fences six feet or less, gates, stairs, driveways, pools, windows, roofing, kitchen or bathroom remodels, and mechanical, electrical, and plumbing repairs. Projects requiring structural review, in historic districts, with open code enforcement cases, or legalizing violations are excluded. The program requires electronic submission of documents and plans prior to an in-person or virtual meeting, with same-day review and approval as appropriate. Reports to the Board are required every six months, and permit fees must be reduced by 10 percent per business day for delays caused by the reviewing department. The ordinance was introduced on 7/14/2026, adopted on 7/21/2026, and becomes effective ten days after enactment unless vetoed. No specific address, parcel, acreage, or applicant is stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Adopted
SAME DAY PERMIT PROGRAM
The document is a legislative item for an ordinance creating a same-day permitting program for certain residential projects in Miami-Dade County. It was adopted by the Board of County Commissioners on 7/21/2026. The ordinance requires the County Mayor or designee to develop and implement a same-day permitting program for eligible applications, including building permits, public works permits, or zoning improvement permits for minor residential projects such as fences, gates, stairs, driveways, pools, windows, roofing, kitchen or bathroom remodels, and mechanical, electrical, and plumbing repairs. Projects requiring structural review, in historic districts, with open code enforcement cases, or to legalize violations are not eligible. The program requires electronic submission of documents and plans prior to a meeting, and reports every six months. If applications are not approved on the same day due to reviewing department delays, the building permit fee shall be reduced by 10 percent per business day. The ordinance is effective ten days after enactment unless vetoed. No specific address, parcel, acreage, or applicant is stated.
- Board:
- Board of County Commissioners
- Date:
- 2026-07-21
- Type:
- Ordinance
- Decision:
- Adopted